Re: [AMBER] skip parallel test

From: David A. Case <case.biomaps.rutgers.edu>
Date: Tue, 5 May 2009 16:34:14 +0100

On Tue, May 05, 2009, Collins Nganou wrote:
>
> I would like to know if it is possible to skip parellel test in amber 10?

Certainly! Running "make test" just tests the serial code. You might also
want to run "make test.serial.QMMM" if you plan to use QMMM. See the top of
$AMBERHOME/test/Makefile for targets that are available.

>
> If yes, how can I do it and what could be the consequences ?

If you don't plan to run parallel jobs, there is not point in running the
parallel tests. But if you do plan to run parallel jobs, you should make sure
the test cases work.

...dac